Dear all
I want to assess river flow changes under natural conditions. There needs to be no reservoir in my study area to do this. In other words, I was looking for a way to deactivate (remove) them from my calculations without any 'Save As' methods. I tried to set the storage value to zero, but the current account does not change, affecting the following years. I appreciate any guidance helping me to solve this issue. Best. |
Subject: Re: No reservoir scenario
Posted: 4/5/2022 Viewed: 7503 times
Dear Mohammad,
If you right-click on your reservoir in the schematic and look at General Info, you can uncheck the box Active in Current Accounts. You will then be able to assign a Startup Year (in the data view) for your reservoir for each scenario if you choose to. Anne |